Dry-process bored pile installation steps using a tripod rig

Detailed process of dry bored piling: setting tripod rig, casing installation, bucket auger boring, rebar cage placement, concrete pouring, and casing withdrawal.

Concrete placement for dry-process bored pile via hopper and tremie chute
01

1. Rig positioning and temporary casing installation

The tripod rig is set precisely over the survey stake marking the pile center and leveled using a plumb line. A starter bore is made using a cylindrical hammer to a depth of 1-1.5 m before installing temporary casing.